Hospital Net Zero

Energy baseline and opportunity screen

Enter 12 months of electricity, fuel and water to get an energy and carbon baseline and a list of systems to investigate first.

What this page is: one calculator that runs in your browser and stores nothing. Sources and limits are on the calculators page; for a linked 42-sheet model use the engineering toolkit.

Limits of this tool. A 12-month comparison, not adjusted for weather, occupancy or operating changes. It is not an IPMVP-verified baseline and must not be called measured and verified savings. Governing documents to consult: IPMVP; ASHRAE Guideline 14.
Energy baseline and opportunity screen12 months
About this tool

What it does: Turns 12 months of electricity, fuel and water into an energy and carbon baseline and points to where to look first.

Background: A baseline is the starting point for every efficiency, solar and storage decision; interval data adds load factor and base load.

Benefit: Shows which systems (chiller plant, controls, steam and hot water, water) deserve measurement and engineering review first.

Equations, units, assumptions and limits

Units: kWh/month, therms/month, kgal/month, kW, ft2, kg/kWh, $/kWh, $/therm; results in kWh/ft2, kBtu/ft2/yr, tCO2, %.

Default assumptions: Example 500,000 ft2 hospital with 12 months of data. Grid factor 0.348 kg/kWh (eGRID2023 national). Flag thresholds (25% electric swing, 70% base-to-peak, 40% summer fuel) are screening rules of thumb, not standards.

Limits: Annual and monthly totals only. Not a weather-normalized baseline or an IPMVP/M&V baseline: the heating degree-day input gives a simple ratio only. Peak and base demand are numbers you enter, not analysis of an interval time series. Natural gas only: other fuels are not included. Opportunity flags tell you where to measure, not what you will save.

Level: screening estimate. It supports planning and prioritizing, not design, procurement or a performance guarantee. Detailed engineering by qualified local professionals is required before any project.

Exactly 12 values from utility bills or the revenue meter. Separate with commas or spaces.
12 values in therms (100,000 Btu). Natural gas only: oil, diesel and other fuels need their own emission factors and are not included. Enter 12 zeros if none.
12 values in thousand gallons, or clear the box to skip water.
eGRID2023 national 0.348. Use your local factor.
Lowest sustained demand from 15-minute data.
Governing constraints. Ventilation rates, pressure relationships, humidity control and clinical requirements limit every opportunity this screen suggests.

Equations: Site EUI = (kWh × 3.412 + therms × 100) ÷ ft². Load factor = (annual kWh ÷ 8,760) ÷ peak kW. Base ratio = base kW ÷ peak kW. Electric swing = (highest month − lowest month) ÷ highest month. Scope 2 = kWh × kg/kWh ÷ 1,000; Scope 1 = natural gas therms × 0.005291 t. Median: ENERGY STAR. Opportunity flags are screening rules of thumb, not standards. Start with at least 12 months; add interval data where available.

Worked example

A 500,000 ft² hospital enters 12 months of data: 22.35 GWh of electricity, 679,000 therms of natural gas and 46,800 kgal of water, with a 3,800 kW peak and 2,300 kW base load. The tool returns a site EUI of 288 kBtu/ft² (about 23% above the ENERGY STAR hospital median), a load factor of 67%, a base load of 61% of peak and 11,370 tCO₂ (7,778 Scope 2, 3,593 Scope 1, with no T&D loss uplift). Electricity swings 31% between February and July, which points first to the chiller plant and pumping. Summer fuel use is 36% of the winter peak, so steam, reheat and hot water are worth a survey. These are places to measure, not savings, and this is not a weather-normalized or IPMVP baseline.

Independent planning estimate using published US government factors. Not endorsed by DOE, EPA, NREL or any agency. Not an audit or a verified inventory. See methods.