Hospital hot water, Legionella control and heat recovery
How to estimate preheat energy and why heat recovery must be designed around the building water management program.
1. Concept
Hospitals use large amounts of hot water, and plant rooms reject heat that could preheat it. Heat-pump water preheating is attractive, but domestic water systems also carry a Legionella risk, so any change to temperatures, storage or flow is a water safety decision as well as an energy decision.
The preheater is only the first stage. Final heating, storage temperature, circulation and the water management program stay in control of safe delivery.
2. Engineering principles
- Energy to heat water = gallons x 8.34 lb/gal x temperature rise / 3,412 Btu per kWh.
- A heat pump delivers more heat than the electricity it uses; its coefficient of performance (COP) falls as the water lift increases and rises with warmer source air.
- Recovered heat is only useful if the heat source and the hot-water demand occur at the same time, or storage bridges them.
- A cooling credit for the room is real only for the share of recovered heat that coincides with useful mechanical cooling.
- Storage and circulation temperatures, dead legs, stagnation and flow are controlled by the water management program.
3. Code and guidance
- ASHRAE Standard 188 requires a water management program for building water systems, and CMS requires hospitals to have policies to reduce Legionella risk. CDC provides toolkits. Commonly cited temperature targets (for example storage at or above 140 degrees F and circulation at or above 120 degrees F) apply subject to your water management program.
- Plumbing, mechanical and electrical codes govern equipment installation, and manufacturers' limits govern heat-pump operating conditions.
4. Worked calculation: preheat energy
- Hot-water demand 3,000 gallons per day, preheated from 60 to 125 degrees F.
- Energy per day = 3,000 x 8.34 x (125 - 60) / 3,412 = 476.6 kWh of heat.
- Per year (365 days) = 173,967 kWh of heat. This is the heat the preheater would need to deliver in this example.
- To estimate electricity use, divide the heat by the COP at the actual room temperature and water lift. A COP of 3 would mean about one third of the heat figure in electricity.
- The 125 degrees F in this example is a preheat temperature, not a storage temperature recommendation.
5. Hospital scenario
A plan proposes using the medical-air compressor room heat to preheat domestic hot water. What conditions must be confirmed before the project proceeds, and who must approve changes to hot-water storage and circulation?
Discuss with your team. There is no single answer; compare your reasoning with the principles above.
6. Assessment
Five original questions with explanations. Your best score is saved on this device only.
7. Practical output: Checklist: heat recovery for domestic hot water
Related tools
Standards and references
- ANSI/ASHRAE Standard 188 Legionellosis: Risk Management for Building Water Systems
- CDC Legionella water management program toolkit
Confirm the edition adopted for your project and jurisdiction. Standards are cited by name only; no standard text is reproduced here.