Review status. Draft for author review. Independent technical review pending. Educational example, not a design basis. Educational and screening material only. It supports qualified professional judgment and does not determine code compliance, replace your hospital's policies or the advice of qualified engineers, clinicians and infection-prevention staff.

1. Concept

A variable-air-volume system supplies air at a constant cold temperature and changes the airflow to each zone to match its load. A box at each zone opens as the load rises and closes as it falls. The central fan slows as the boxes close, which saves fan energy.

The box cannot close completely. A minimum airflow is needed for ventilation, air movement, controls to work and, in some spaces, pressure or air-change requirements. At the minimum airflow a zone that needs less cooling than the minimum supply provides is overcooled, so the box adds reheat. That is the main energy weakness of a simple VAV system.

Understanding the minimum airflow and the reheat that follows from it lets you find where a VAV system wastes energy and where it can be improved without hurting ventilation or clinical conditions.

2. Engineering principles

3. Code and guidance

4. Worked calculation: a VAV box with a reheat coil

  1. A zone has a design sensible cooling load of 6,000 Btu/h, a room setpoint of 75 F and a supply air temperature of 55 F.
  2. Maximum cooling airflow = 6,000 / (1.08 x 20) = 278 cfm.
  3. With a 30 percent minimum setting the minimum airflow is 83 cfm. The turndown ratio is 3.33.
  4. In winter the zone loses 4,000 Btu/h. At the minimum airflow the discharge temperature needed is 75 + 4,000 / (1.08 x 83) = 119 F, which is 44 F above the room. This is much more than the 20 F often used as a practical limit.
  5. To keep the discharge within 20 F the heating airflow should be 4,000 / (1.08 x 20) = 185 cfm. Dual-maximum control raises the airflow to this value in heating rather than overheating the air.

5. Hospital scenario

A VAV zone serving a clinic area is cold in winter although the reheat valve is fully open. Describe the readings you would take (box airflow, discharge temperature, supply air temperature, room temperature), what the numbers would show if the discharge temperature is very high and the airflow is at minimum, and what control change you would consider.

Discuss with your team. There is no single answer; compare your reasoning with the principles above.

6. Assessment

Five original questions with explanations. Your best score is saved on this device only.

Question 1. A zone has a 10,800 Btu/h sensible load, a 75 F room and 55 F supply air. Maximum cooling airflow is closest to:
Question 2. Why does a VAV box need a minimum airflow?
Question 3. What is the main energy weakness of a simple VAV system with reheat?
Question 4. A very hot discharge temperature at minimum airflow in heating usually:
Question 5. Why are some critical clinical spaces not served by simple variable-airflow control?

7. Practical output: Verification checklist: VAV zone or minimum-setting change

Related tools

Standards and references

Confirm the edition adopted for your project and jurisdiction. Standards are cited by name only; no standard text is reproduced here.

← Energy codes and heat recoveryNext: Heat pumps, dedicated outdoor air and radiant cooling →