Planning a utility shutdown and infection control risk assessment

How to plan a planned shutdown or renovation in an occupied hospital so that patient care, redundancy and infection control are protected.

Track 6: Healthcare project managementIntermediate30 minutesNot started

Review status. Draft for author review. Independent technical review pending. Educational example, not a design basis. Educational and screening material only. It supports qualified professional judgment and does not determine code compliance, replace your hospital's policies or the advice of qualified engineers, clinicians and infection-prevention staff.

1. Concept

Every planned shutdown in an occupied hospital is a risk decision. The question is never only how to do the work, but which patients and services depend on what is being shut down, what backup exists, and how the work will be verified and reversed.

An infection control risk assessment (ICRA) rates the construction activity against the vulnerability of the patients nearby and sets the precautions required. Interim life safety measures (ILSM) address temporary fire-safety impairments.

2. Engineering principles

3. Code and guidance

4. Worked calculation: capacity margin during a chiller shutdown

  1. The central plant has 4 chillers of 600 tons each. The summer peak is 1,500 tons.
  2. With one chiller out for maintenance, capacity = 3 x 600 = 1,800 tons. Margin = 1,800 - 1,500 = 300 tons (20 percent). The plan is feasible, but only one failure from trouble.
  3. If the work needs two chillers out, capacity = 1,200 tons. Shortfall = 300 tons (20 percent of peak).
  4. A shortfall means the work must move to a cooler period, use temporary cooling, or reduce load by agreed clinical measures. It must not proceed on hope.

5. Hospital scenario

A contractor proposes a four-hour shutdown of an electrical panel serving a pre-op area and a sterile storage room, starting at 9 a.m. on a weekday. What approvals, alternative supply and verification do you require before agreeing?

Discuss with your team. There is no single answer; compare your reasoning with the principles above.

6. Assessment

Five original questions with explanations. Your best score is saved on this device only.

Question 1. Which factor most increases the required ICRA precautions?
Question 2. A plant has four 600-ton chillers and a 1,500-ton peak. Two are shut down. The result is:
Question 3. Interim life safety measures are intended to:
Question 4. Before restarting a system after shutdown you should:
Question 5. A good shutdown plan always includes:

7. Practical output: Checklist: critical shutdown plan

Related tools

Standards and references

Confirm the edition adopted for your project and jurisdiction. Standards are cited by name only; no standard text is reproduced here.

← Responding to a utility power failureNext: Refrigerants and anesthetic gases as Scope 1 emissions →