Life-cycle cost for hospital projects
How to compare a project's lifetime benefits and costs in today's money, and which assumptions most change the answer.
1. Concept
A project that saves money every year but costs a lot today must be judged over its life, not on its first cost. Life-cycle cost analysis converts future savings and costs into present value so they can be compared.
Hospitals add complexity: long service lives, tight capital budgets and the need to protect clinical operations. The same method still works, but the assumptions must be honest.
2. Engineering principles
- Net present value (NPV) = present value of savings minus present value of added costs minus initial cost.
- Savings-to-investment ratio (SIR) = present value of savings divided by present value of costs. Above 1 means savings exceed costs over the study period.
- Simple payback = initial cost divided by net annual savings. It ignores timing and anything after payback, so use it as a first screen only.
- Use real (inflation-free) discount rates with real energy-price escalation, or nominal with nominal. Do not mix them.
- Test the result by changing savings, cost, discount rate and life. A decision that survives these tests is robust.
3. Code and guidance
- The U.S. Federal Energy Management Program (FEMP) and NIST publish life-cycle costing methods and annual discount rates, which many public and private evaluations follow.
- Taxes, incentives, replacement costs and residual value are excluded from simple screens and need separate treatment.
4. Worked calculation: an efficiency project
- Initial cost $500,000, year-1 savings $90,000, added O&M $10,000 a year, study period 20 years, real discount rate 3 percent, no escalation.
- Present value factor for 20 years at 3 percent = (1 - 1.03^-20) / 0.03 = 14.877.
- PV of savings = 90,000 x 14.877 = $1,338,973. PV of O&M = 10,000 x 14.877 = $148,775.
- NPV = 1,338,973 - 148,775 - 500,000 = $690,198.
- SIR = 1,338,973 / (500,000 + 148,775) = 2.06. Simple payback = 500,000 / (90,000 - 10,000) = 6.25 years.
- If savings are 30 percent lower than expected, the NPV drops sharply. Always test the downside.
5. Hospital scenario
Two projects have the same NPV. One saves energy and also removes a safety risk; the other saves more energy but adds a maintenance burden. How do you present the choice to your board?
Discuss with your team. There is no single answer; compare your reasoning with the principles above.
6. Assessment
Five original questions with explanations. Your best score is saved on this device only.
7. Practical output: Checklist: life-cycle cost screening
Related tools
Standards and references
- NIST Handbook 135, Life-Cycle Costing Manual for the Federal Energy Management Program
- FEMP annual discount rates and energy price indices
Confirm the edition adopted for your project and jurisdiction. Standards are cited by name only; no standard text is reproduced here.